                        Health, Safety & Environmental Bulletin No 019

                                           M Mott –7 February 2005


                                                    Material Fall



           A recent incident occurred on a client’s site where 35 scaffold poles 21ft long dropped 16m to
           the ground.

           This  was  a  result  of  the  load  being  incorrectly  slung  with  lifting  chains  by  an  unqualified
           person working under the direction of a banksman.
























           The photographs below show the correct method of lifting scaffold poles and boards - use
           double wrapped webbing slings, and the slinging  of the load must only to be carried out by a
           competent trained person.  The slinging  of scaffold materials with chains  is not permitted.