                                              Shallow Buried Cable



           We  have  recently  had  a    safety  observation
           reported  where  a  buried  cable  was  found  only
           millimetres below the surface.

           The crew was on site to breakout around a MID
           in  order  to  survey  the  footplate,  so  plans  for  a
           MID replacement can be produced.

           The  crew  LOTO’d  the  MID  supply  and  CAT
           scanned  the  area  to  identify  the  supply  cable.
           The CAT scanning identified that the cable was
           just below the surface.

           The  crew  cautiously  started  digging  200mm
           away  from  the  identified  cable,  when  a  large
           section  of  the  concrete  broke  off  exposing  the
           cable which was only 30mm below the surface.

           This  incident  shows  the  importance  of  CAT
           scanning  and  the  need  to  be  wary  of  shallow
           cables  and  services  when  breaking  the  surface
           (digging or drilling).

           Ensure  you  always  follow  the  safe
           digging procedures, check the service
           drawings, CAT scan and record your
           findings  on  the  ground  disturbance
           form.  MIDs will always have at least
           one  cable  going  to  them,  so  ensure
           you identify it before digging/drilling
           around the MID.